News

Back

Gladstone Port – Planned Maintenance Notice

Planned Shutdown 23 July To 27 July 2018
Terminal: R G Tanna Coal Terminal
Plant: Shiploader No.2 on Berth No.1.
Duration: 5 days.

The main work for the Shiploader No.2 Shutdown includes:

  • Inspect and repair SL2 telescopic chute.
  • Repair oil leak on gearbox, CC7A Gladstone side.
  • Upgrade CC7A drive coupling on Gladstone and Rocky sides.
  • Install new steelwork to support replacement Transformer on SL2.
  • Abrasive blast and paint underside of SL2 MCC Room.
  • Structural repairs on SL2 Tripper upper end.
  • Cold repairs on CC6 belt.
  • Repair, abrasive blast and paint SL2 Tripper rail between CC6 and CC6A.
  • Service and calibrate CC5 belt weighers.
  • Tiling repairs in transfer chutes in SL2 system.
  • Sample Plant 1 maintenance.
  • Belt cleaner maintenance.
  • General maintenance of the Shiploader No.2 system and conveyors.
Previous Story

Ben Line Agencies – Philippines – Cruise Sector

Read More